A grade separation (underpass, overpass or trench) removes the conflict for good: no gate, no wait, no collision. Here's what completed projects removed, and which cities are building theirs now.

CompletedFunded / under way

Completed projects

ProjectOpenedCrossings removedVehicles/dayTrainsDelay removedSafety recordCostSource
25th Ave grade separation (CREATE)Bellwood / Melrose Park, IL · Union Pacific2016119,00052 freight + 59 Metra28,400 hours a year eliminated130+ crashes in the project area before$41.0MCREATE program ↗
San Gabriel Trench (ACE)San Gabriel, CA · Union Pacific2018490,00018, projected 611,744 vehicle-hours of delay eliminated10 collisions, 2 deaths in the prior decade$293.7MACE Project ↗
Durfee Ave grade separation (ACE)Pico Rivera, CA · n/a2022113,000n/an/a10 collisions, 5 deaths since 1981$107.8MCity of Pico Rivera ↗
ReTRAC rail trenchReno, NV · Union Pacific200511n/a14, projected 24+n/aFaster emergency response (qualitative)$280.0MTransportation Research Board case study ↗
Alameda CorridorLos Angeles, CA · UP · BNSFn/a200+n/aSpeeds up from 15 to 40 mphn/aOver 1,007,659 tons of CO₂ avoidedn/aAlameda Corridor Transportation Authority ↗
130th St & Torrence Ave (CREATE)Chicago, IL · Norfolk Southernn/a227,40050+ freight240+ vehicle-hours a day beforeTrains blocked the road into a 4,000-job Ford plant up to 20 minn/aCREATE program ↗
Central Rail Corridor (elevated track)Wichita, KS · BNSF · UPn/an/an/a40Crossings had been blocked up to 30 min eachThree arterials now pass under the tracks$105.0MAmerica's Transportation Awards ↗

"n/a" means the source didn't report it. San Gabriel's and Reno's delay figures don't state a time unit; we show them as published. Reno opened to trains in 2005, with work finishing in 2006.

Funded or under way

CityProjectStatusWhyFundingSource
Moore, OKSE 4th St / SH-37 underpass (BNSF)Over 50% complete; late spring 202715,500 vehicles a day; 115 emergency vehicles blocked in 20 months~$30MSource ↗
Olathe, KSClose Woodland Rd crossing; 119th St flyover (BNSF)Federally funded (FY2022 RCE)68–88 trains a day on the line$17,987,495 federalSource ↗
Houston, TXFour East End underpasses (UP)Federally funded (FY2022 RCE)Trains stop 5–10 times a day, ~30 min$36,916,200 federalSource ↗
Pelham, ALBridge over two CSX crossingsFederally funded (FY2022 RCE)Responders cut off when CR 52 is blocked$41,766,038 federalSource ↗
Davis, OKNew siding, 2 closures, 3 upgrades (BNSF)Federally funded (FY2023–24 RCE)One stopped train blocks all three crossings$25,448,000 federalSource ↗
Fort Worth, TXBonds Ranch Rd overpassFederally funded (FY2022 RCE)~36 trains a day; responders stuck over an hour$17,187,552 federalSource ↗
Hammond, INGovernors Pkwy overpassFederally funded (FY2022 RCE)School routes blocked 4–7 hours$7,029,392 federalSource ↗
San Antonio, TXRittiman Rd grade separationFederally funded (FY2022 RCE)50 reports over an hour at nearby Walzem Rd$4,886,512 federalSource ↗

What it costs

A typical overpass or underpass runs $10M–$30M, and Texas estimates $10M–$15M per rail grade separation (Texas A&M Transportation Institute). Trenches and corridors cost far more: $105M–$294M above.

TTI ↗

What it fixes

Grade separation "eliminates collisions between trains and roadway users by removing the point of intersection between the modes." It also ends blockages at that street permanently.

FRA Grade Crossing Toolkit ↗

The catch: time

Moore's SE 4th St underpass was bond-funded in 2018 and is due in 2027. Fixes take years, and the competitive grant applications that fund them need evidence. That's the gap Trainwatch fills: a verified record now, and live detours until the fix is built.